Sizing a Charging Hub: Ports, Power and Queue Times

Row of EVs charging at commercial wall-mount charging stations in an office parking lot
Size a hub by making three numbers agree: ports from the busiest hour, power from the confirmed supply, and the queue your own arrival pattern creates.

EVDANCE Insights · EV Charging Guides

A hub is sized by making three numbers agree: the ports, the total power the supply can deliver, and the queue your busiest hour creates. Ports come from the arrival pattern; power per port from the energy a stop must deliver inside its dwell; the supply is a confirmed figure from the utility, not an assumption. Where the three disagree, the smallest one is your real capacity.

Key Takeaways

  • Size from the busiest evidenced hour: arrivals times session time gives the ports busy at once.
  • Queue behaviour is read from your own arrival pattern and session records, never from a standard table.
  • Phase the ports; build the supply works once. Corridor-class 150 kW ports sit outside EVDANCE’s compact DC range.
Row of EVs charging at commercial wall-mount charging stations in an office parking lot
Ports, delivered power and arrivals, sized against each other.

The Demand Side: Count the Busiest Hour You Can Evidence

Averages hide queues: a hub comfortable on a daily average can fail every Friday evening, because arrivals bunch and dwell shrinks at the same hours. Start from evidence: counted arrivals at a comparable site, the host’s peak hours, or your first-phase records. Session time is then arithmetic, not opinion: the energy each stop must deliver, divided by the power the port actually delivers. The U.S. DOT’s bands frame the choice: Level 2 at 7–19 kW suits long dwells, DC fast at 50–350 kW suits short ones.

The Sizing Worksheet

Worksheet lineYour inputWhere it comes from
Peak arrivals per hourVehicles wanting a charge in the busiest recurring hourSite counts, host trading peaks, or first-phase records
Energy per sessionThe kWh a typical stop must add before the driver leavesYour vehicle mix and stop purpose
Session timeEnergy per session divided by delivered power per portYour arithmetic; allow for taper on DC sessions
Ports neededPeak arrivals multiplied by session time in hours, rounded upPorts busy at once at the peak
Total power checkPorts multiplied by per-port power, set against the site supplyThe utility’s written connection offer
Queue testWhat happens at the peak with one port out of serviceYour decision: more ports, more power per port, or an accepted short wait

The total power check is the line most often skipped. Ten ports at full rating can exceed what the connection offers; then either per-port power falls or the port count does. The worksheet, not the brochure, must say which one your site picked. If supply binds, the full plan’s civil works can still be built once, with ports phased in as records justify them.

EVs charging at wall-mounted stations in a parking garage
Ports sharing one supply are checked as a total.

Queue Times Are Read From Your Pattern, Not a Formula

Your wait time cannot be read from a table: it depends on how sharply your arrivals bunch, how long drivers stay plugged in after charging ends, and whether a queue is visible enough to send drivers elsewhere. Queues that form at the same hours each week are sizing evidence — the worksheet inputs were too kind. Queues that form twice a year may be an accepted design choice. Once the first phase runs, platform records replace estimates with your site’s own pattern — that, not a formula, releases the next phase of ports. Choosing the site itself comes first: a hub cannot be sized out of a location problem.

The Hardware Mix, and EVDANCE’s Place in It

This worksheet sizes the site; pricing it from quotes is a separate exercise. On hardware, hubs mix classes by dwell: DC for short stops, AC for long ones. EVDANCE supplies the compact end of that mix. The EV-RHDC30K-L compact DC charger (22 kW DC, OCPP 1.6J, IP54) serves short-dwell light-duty stops at compact sites, below the 50–350 kW corridor class. The EV-AC03201T dual-connector AC station (two Type 2 connectors, up to 43 kW shared, OCPP 1.6J, RFID, IP54) covers longer dwells, two ports per unit. Be plain about the top end: a corridor hub specified around DC ports of at least 150 kW — the NEVI level for funded corridor stations — is beyond EVDANCE’s DC class. Hub plans can be discussed with our commercial charging team via contact us.

Frequently Asked Questions

How many ports should a hub open with?

The number your busiest-hour worksheet produces, with the groundworks sized for the full plan. Opening with every planned port strands capital in idle hardware; too few teaches drivers that your site queues.

Is more power per port better than more ports?

It depends which constraint binds. If sessions are long because each stop needs much energy, power per port shortens them and frees ports. If many drivers arrive at once needing little each, ports are the constraint and power buys nothing.

Does a queue at peak times mean the hub is undersized?

Only if it recurs. A queue at the same hours in your session records is evidence the inputs were optimistic. A rare queue on an exceptional day can be a deliberate, documented design tolerance.

Related Reading

Sources & Standards

EVDANCE · EV Charger Manufacturer

Looking for a reliable EV charger supplier?

Portable EV chargers and wallbox home chargers for distributors, installers and brands. Tell us your market and we will reply with a quote.

  • OEM / ODM from 50 units
  • 3-year standard warranty
  • FOB / DDP shipping worldwide
Share the Post:

Related Posts

0