Choosing Between 7 kW, 11 kW and 22 kW for a Commercial Car Park

Row of EVs charging at commercial wall-mount charging stations in an office parking lot
Choose the class by dwell: output x the stay your car park gets, on the phases your supply has - 7 kW single-phase, 11 or 22 kW three-phase.

EVDANCE Insights · EV Charging Guides

Choose by dwell, not by the biggest number. The right class is the one whose output, multiplied by the stay your car park actually gets, covers the energy a visit needs — on the phases your supply has. A 7 kW post on a three-hour stay delivers more useful energy than a 22 kW post on a thirty-minute stop, so observe the stay first and let the arithmetic choose.

Key Takeaways

  • The three classes are supply shapes: 7 kW single-phase, 11 kW three-phase at 16 A, 22 kW three-phase at 32 A.
  • Delivered energy is power × the observed stay — run that arithmetic before choosing a class.
  • The car’s onboard charger caps every session; the post’s rating is a ceiling, not a promise.
  • Phase availability and concurrent load are site confirmations for the electrical design, never assumptions.
Row of EVs charging at commercial wall-mount charging stations in an office park
Match the class to the stay, the cars and the supply.

The Three Classes Are Three Supply Shapes

The ratings differ because the supply differs. The roughly 7 kW class is single-phase at 32 A; the 11 kW class is three-phase at 16 A per phase; the 22 kW class is three-phase at 32 A per phase. The U.S. DOT places Level 2 charging at 7–19 kW, adding 10–20 miles of range per hour; 22 kW is the three-phase class above that band’s stated top. Our explainer on single-phase vs three-phase charging works through the supply side. One ceiling applies at every class: the car’s onboard charger. A car accepting 11 kW AC takes 11 kW from a 22 kW post — the class is a ceiling, never a promise.

Run the Dwell Arithmetic

Delivered energy is power × time, assuming the car accepts the full rate throughout — an upper bound to compare against the energy your visitors need. The stays below are examples, not measurements of your site:

Stay you observe7 kW class delivers up to11 kW class delivers up to22 kW class delivers up toSpecifier’s reading
45 minutesAbout 5 kWhAbout 8 kWhAbout 16 kWhShort stays reward higher classes — where cars accept them and the supply feeds them
2 hoursAbout 14 kWhAbout 22 kWhAbout 44 kWhCovered at any class; the choice turns on turnover, not energy
4 hoursAbout 28 kWhAbout 44 kWhAbout 88 kWhHalf-day stays are covered in full by the lower classes for most cars
8 hoursAbout 56 kWhAbout 88 kWhAbout 176 kWhMost batteries are satisfied long before the post is the limit

Read it against your own evidence: observed stays, and the energy a visit needs to add. Our timing guide shows how long charging takes at 7, 11 and 22 kW from the driver’s side — the same arithmetic, read from the supply side.

Confirm the Phases Before You Specify

  • Single-phase supply only: the roughly 7 kW class is the ceiling per post. More posts at that class may serve better than one oversized point; the total is a load decision for the electrical design.
  • Three-phase available: 11 and 22 kW open up — but board availability is not capacity for every post at once; the concurrent total is what the design carries.
  • Breaker sizing follows the NEC continuous-load rule: the breaker is 125% of the charger current — a 32 A charger takes a 40 A breaker. The rule scales every class.
  • Nothing forces one class site-wide. Rows with different stays can be specified differently; the supply that totals them is designed once.

The Classes in the EVDANCE Range

Each class above maps to stated models. At roughly 7 kW single-phase, the EV-ACS3210E is a 32 A Type 2 portable charger at about 7 kW, and the EV-ACS3210T is its NACS counterpart at about 7.7 kW. At 11 kW three-phase, the ACS1605PE runs 16 A three-phase through a CEE five-pin plug. At 22 kW three-phase, the EV-ACT3204PE is a 32 A wallbox and the EV-ACS3205PE a 32 A portable on a CEE 32 A plug. Project teams can discuss a mixed-class layout through our commercial EV charging page or contact us.

EVDANCE EV-ACT3204PE 22 kW three-phase wallbox
The 22 kW class: three-phase at 32 A.

Frequently Asked Questions

Is 22 kW always the best choice for a commercial car park?

No. It earns its capacity only where stays are short or visiting cars accept high AC rates, and it needs three-phase supply. On long stays the extra capacity idles; lower classes deliver the same energy before the car leaves.

What if our supply is single-phase only?

Then the roughly 7 kW class is the per-post ceiling, and the design question is how many posts the supply carries at once. Confirm it with the project’s electrical design — a supply upgrade is a separate project decision, not a charger feature.

Can different rows of one car park use different classes?

Yes. Specify each row against the stay observed there, and let the electrical design total the mix. The constraint is the shared supply, not uniformity.

Related Reading

Sources & Standards

EVDANCE · EV Charger Manufacturer

Looking for a reliable EV charger supplier?

Portable EV chargers and wallbox home chargers for distributors, installers and brands. Tell us your market and we will reply with a quote.

  • OEM / ODM from 50 units
  • 3-year standard warranty
  • FOB / DDP shipping worldwide
Share the Post:

Related Posts

0