There is no verified price list for setting up a charging station by site type, and any table that offers one is inventing its numbers. What does exist is a set of U.S. DOE-cited ranges per charger class — public Level 2 at about $3,500 equipment plus $2,500 installation per connector, DC fast charging at about $38,000–$90,000 equipment plus $20,000–$60,000 installation per unit — and the fact that site types load those ranges differently. Workplace sites stress bay count and cable runs; depots stress supply capacity; corridor sites stress the grid connection. Your total is assembled from quotes, by type, using the method below.
Key Takeaways
- Setup cost is priced per charger class, not per site type; site types differ in which cost drivers dominate.
- The sourced anchors are DOE-cited U.S. ranges: Level 2 about $3,500 plus $2,500 per connector; DC fast about $38,000–$90,000 plus $20,000–$60,000 per unit.
- Assemble the total from line-by-line quotes against a frozen specification; carry the utility line as provisional.
- Compact DC is quoted on its own lines — never priced from the fast-charging class ranges.

Cost Drivers by Site Type
| Site type | Hardware class | Dominant cost drivers | DOE anchor that applies |
|---|---|---|---|
| Workplace car park | Level 2 ports, several bays | Number of bays; distance from the switchboard to the far bays; access control for staff and visitors | Public Level 2 range, applied per connector |
| Hotel and retail host | Level 2 for dwell-length stays | Bay count; signage and bay marking; guest access and payment arrangement where fitted | Public Level 2 range, applied per connector |
| Fleet depot, light vehicles | Level 2 at scale; compact DC for quick turnarounds | Supply capacity for simultaneous charging; trenching across a working yard; layout around vehicle movements | Level 2 range per connector; compact DC quoted as its own lines |
| Public corridor or fast site | DC fast charging, 50–350 kW class | Grid connection and utility-side works; civil works; programme compliance where funded — 24/7 opening, contactless payment, uptime duties | DC fast range per unit, with the utility line carried as provisional |
Read the table as a map of where quotes will move, not as prices. A workplace with spare switchboard capacity and bays beside the building can land near the bottom of its class range; a depot that needs a new supply and a hundred metres of trench will not, and no published source converts those conditions into a per-type total. The general commercial installation cost breakdown covers the shared lines in more depth.
Assembling Your Number
- Freeze the specification per site. Ports, power class, connectors, access and payment scope on one page; every quote is priced against it.
- Quote the lines separately. Equipment, electrical work, civil works and commissioning as distinct lines, so a cheaper quote shows which line it shrank.
- Carry the utility line as provisional. Only the utility’s written connection offer prices it; mark it open until the offer lands.
- State exclusions in writing. Freight, extra foundations, utility charges and spares are the usual gaps between quotes.
- Keep incentives out of the stack. Confirm a programme’s current terms before netting anything off; the U.S. 30C credit no longer applies to property placed in service after June 30, 2026.

Where EVDANCE Hardware Sits in the Table
For workplace and host sites, the EV-AC03201T dual-connector AC station — two Type 2 connectors, up to 43 kW shared, OCPP 1.6J, RFID, IP54 — puts two connectors on one floor-standing unit, which is why shared bays are quoted per connector rather than per post. For depot turnarounds, the EV-RHDC30K-L delivers 22 kW DC: below the 50–350 kW fast class, so its equipment and installation are quoted as their own, smaller lines rather than read off the DC range — and its listing does not name the DC connector variant, a written confirmation before ordering. Site plans and frozen specifications can be brought to the commercial charging team via contact us.
Frequently Asked Questions
Which site type is cheapest to set up?
Per connector, Level 2 classes carry the lowest published anchors. Site totals are a different matter: port count and site works decide them, and a small corridor site can out-cost a large workplace installation on the utility line alone.
Does the DOE installation range include a grid upgrade?
The cited range is the published figure for installation in a U.S. public context; utility-side work is priced by the utility for the specific site. Carry that line as provisional until the written connection offer arrives.
Can I subtract grants or tax credits from the setup cost?
Only once a programme confirms your project in its current terms. Schemes change — the U.S. 30C credit closed to property placed in service after June 30, 2026 — so an unconfirmed incentive never belongs in a cost stack. DSIRE tracks current U.S. state programmes.
Related Reading
- How Much Does It Cost to Install a Commercial EV Charging Station?
- How Much Do Commercial EV Chargers Cost?
- Why Is DC Fast Charging So Expensive?
- What Affects EV Charger Installation Cost? 8 Factors to Check