A charger permit is mostly a paperwork exercise, and the inspection at the end is a comparison against that paperwork. For a 48 A hardwired unit like the EV-ACT5006T, the file usually has four pieces: the application form, the charger’s specification and listing documents, a load-calculation summary, and a simple site plan. Get the file right and the inspection becomes a formality.
Key Takeaways
- The permit file for a 48 A hardwired charger has four pieces: form, product documents, load calculation, site plan.
- The load summary carries the headline figure: 48 A continuous, sized at 125%, on a 60 A breaker.
- The inspection at the end compares the finished work against this file — the paperwork is the standard.
- Your electrician normally prepares and files the pack; keep the signed-off permit afterwards.
The Four Pieces of the Pack
- The application form. The property, the owner, the licensed installer, and the scope of work in plain terms: a new dedicated circuit for a wall-mounted Level 2 charger.
- The product documentation. The specification sheet for the exact model being installed — for the EV-ACT5006T: up to 48 A, single-phase 208–240 V, hardwired — plus its certification listing. The listing is what lets the reviewer confirm the equipment itself is approved for the job.
- The load-calculation summary. A short calculation showing the home’s electrical service can carry the new load. The headline figure the reviewer looks for: EV charging is a continuous load, sized at 125% under the National Electrical Code, so a 48 A charger goes in the file with a 60 A breaker.
- The site plan. Where the charger mounts, where the panel is, and the route between them. For a home job this is usually a simple sketch, not an architect’s drawing.

| Document | Who normally prepares it | What the reviewer is checking |
|---|---|---|
| Application form | Electrician, with the owner’s details | The work is described accurately and completely |
| Spec sheet and listing | Electrician, from the manufacturer’s documents | The equipment is certified and matches the application |
| Load-calculation summary | Electrician | The service can carry a 48 A continuous load on a 60 A breaker |
| Site plan | Electrician, sometimes with the owner | Location, panel and cable route are sensible and as described |
The EV-ACT5006T’s Numbers, as They Appear in the File
The EV-ACT5006T 48A Level 2 wall charger contributes a short list of facts to the pack: 48 A output (11.5–12 kW), a hardwired connection on a new circuit, a NACS connector on a 7.6 m cable, and ETL, FCC and CE marks on the product page. If the mounting wall is outdoors, the IP65/IP66 enclosure rating goes into the file as well. The circuit numbers behind the application follow the same sizing logic as our guide to what size wire an EV charger needs — the paperwork and the installation are two views of the same job.

After Filing
The sequence from there is standard: the permit is issued, the electrician installs to the file, and the final inspection compares the finished work against it — breaker size, dedicated circuit, protection, and the installed unit matching the documents. Keep the signed-off permit with your installation records afterwards; it is the proof the work was approved, and the document a future buyer, insurer or electrician may ask for. How permits and approvals fit the wider process is covered in our guide to EV charging station permits and approvals.
Frequently Asked Questions
Who files the paperwork — me or my electrician?
Usually the electrician prepares and files the pack as part of the job, and the homeowner supplies the property details and signs where required. Practice varies by city and county, so confirm who files when you book the work — and see whether you can install a Level 2 charger yourself for how the roles divide.
Does the plug-in version need the same paperwork?
Normally not. The pack exists because a new circuit is being created. Plugging a charger into a suitable outlet that already exists adds no wiring, so in most areas there is nothing to permit — but local rules decide, so check before assuming.
What happens if the reviewer asks for changes?
Corrections at the paperwork stage are routine: a clearer site plan, a revised load calculation, a different document for the listing. Your electrician resubmits. It is far cheaper to fix the file than to fix a finished installation that does not match it.
Related Reading
- How to Get an EV Charging Station License: Permits and Approvals
- Can I Install a Level 2 Charger Myself?
- What Size Wire Do You Need for an EV Charger?
- How Many kW Is a Level 2 Charger?