EV-AC03201T Commissioning Checklist for Installers

Commissioning a dual-connector station ends with a signed record: identity, supply, both connectors session-tested, platform verified, RFID tried, handover.

EVDANCE Insights · EV Charging Guides

Commissioning a dual-connector station should end with a record the operator can file, not a verbal “all working”. This checklist covers the record side of the job: station identity, the supply that feeds it, a session test recorded on each connector, the platform connection verified, RFID test cards tried, the driver flow checked on the touchscreen, and a signed handover. Procedures, instrument steps and pass values belong to the installer, the manual and your market’s wiring rules — none are listed here, because a checklist records that tests were done and what they showed.

Key Takeaways

  • Commissioning ends with a signed record: identity, supply, both connectors tested, platform verified, access tried, handover.
  • On a dual-connector station, the second connector and the platform link are separate record lines — never assumed.
  • Procedures and pass values belong to the installer, the manual and local rules, not to a checklist.
  • File the record with the site’s electrical documents; it later supports warranty, maintenance and funding claims.
EVDANCE EV-AC03201T dual-connector AC charging station
Both connectors, the platform link and the card set are commissioned as one system.

What Gets Recorded

Record itemWhat to record for this stationWhy it matters later
Station identityModel, nameplate serial number, site and the two bays it servesWarranty and support start from the serial number
Supply recordThe distribution board and protective device feeding the station, and the capacity assessment it was sized againstThe next electrician should not have to work out which circuit is the station’s
Connector A session testA completed session — start, charge, stop — with the energy figure as shownProves the connector works as a system, not just that it powers on
Connector B session testThe same record, on the second connectorHalf the asset: an untested second connector is an unverified charger
Platform connectionThe station visible in the operator’s back office over OCPP 1.6J, with test sessions from both connectors in the platform recordA station the platform cannot see cannot be billed, reported or fault-flagged
Access testRFID test cards presented at the station, results recorded; the card set handed to the operatorAccess is half the product at a public site — test it while the installer is still there
Driver flowThe 7-inch touchscreen walked end to end as a driver meets it, from first screen to session endThe driver’s first minute decides your support calls; catch confusion at handover
Sign-offInstaller identity, date and signature; the operator countersigns; a copy stays with the operatorAn unsigned record is an opinion; a signed one is evidence

What This Checklist Deliberately Leaves Out

How each test is performed, with which instrument, and against which limit is set by the manual and the wiring rules of the country of installation — the IET Code of Practice is one example of the guidance installers work to.

Those values differ by market, so they do not belong in a general checklist. What does not differ is the shape of the record: categories performed, results noted, names against them. A blank line while the installer is still on site is a question; a blank line found a year later, mid-claim, is a problem.

EV-AC03201T floor-standing dual-connector AC station
Connector B gets its own session record: on a dual-connector station, half the asset is the second connector.

The First Week After Handover

  • File the record with the site’s electrical documents, next to the invoice and the warranty terms.
  • Watch the platform: both connectors should show real sessions in the first days of use.
  • Keep the RFID test cards labelled and stored apart from live cards.
  • Note the support route in the record: the installer first for the installation, EVDANCE under the 3-year standard warranty for the station.

The EV-AC03201T is a floor-standing dual-connector AC station — two Type 2 connectors, up to 43 kW shared (22 kW per connector), OCPP 1.6J, RFID, a 7-inch touchscreen and an IP54 enclosure — so its record covers two connectors and a network link, not a single outlet. The same records later support maintenance plans and funding evidence. Questions go through the contact page; see also the commercial charging range.

Frequently Asked Questions

Is the commissioning record the same as the invoice?

No. An invoice proves the job was done and paid for; the record proves what was tested — both connectors, the platform link, the access cards. Ask for it before sign-off, while producing it costs the installer minutes.

The back office shows only one connector. Are we finished?

No. Until both connectors appear in the platform and each has a recorded test session, the station is half-commissioned. Have it resolved before the handover is signed — afterwards it becomes a fault report instead of a commissioning item.

Where do the pass values come from?

From the manual and your market’s wiring rules, applied by the installer with instruments. The checklist fixes the categories; judging the numbers is the installer’s job, noticing a missing category is the operator’s.

Related Reading

Sources & Standards

EVDANCE · EV Charger Manufacturer

Looking for a reliable EV charger supplier?

Portable EV chargers and wallbox home chargers for distributors, installers and brands. Tell us your market and we will reply with a quote.

  • OEM / ODM from 50 units
  • 3-year standard warranty
  • FOB / DDP shipping worldwide
Share the Post:

Related Posts

0