EV-ACS3205PE Load Planning: How Many Units One Supply Can Feed

Each EV-ACS3205PE draws 32 A per phase at full rate, so the count is your supply's spare per-phase capacity divided by 32 - set by an electrician's load calculation.

EVDANCE Insights · EV Charging Guides

The count is set by one division: the supply’s spare capacity per phase, divided by 32. Each EV-ACS3205PE at full rate draws 32 A per phase, continuously, so two units ask the supply for 64 A per phase and three for 96 A — before anything else the building uses. Portables change how the chargers connect — CEE sockets on a distribution board — not the arithmetic.

Key Takeaways

  • Each unit draws 32 A per phase at full rate; N units draw N × 32 A per phase, sustained for hours.
  • The count is the electrician’s stated spare capacity divided by 32 — after the building’s other loads.
  • Sockets cap the physical plan; staggered windows and moving units are the usage routes.
  • Automatic load sharing is not stated for this model — confirm it in writing before designing around it.
EVDANCE EV-ACS3205PE 22 kW three-phase portable charger with CEE plug
Each EV-ACS3205PE is one 32 A-per-phase block of load, wherever it is plugged in.

The Combined Draw, in a Table

Everything here is arithmetic on the unit’s stated input — 32 A per phase, about 22 kW. Units charging at the same time add line by line:

Units charging at full rateCombined draw per phaseCombined power
132 AAbout 22 kW
264 AAbout 44 kW
396 AAbout 66 kW
4128 AAbout 88 kW

Charging is a continuous load: those amps flow for hours, not minutes, so everything is planned around the sustained figure. The worst case is every unit drawing at once — on a shared site, exactly what happens when the whole fleet comes home together. Plan for that row, or arrange that it never occurs.

Three Things Set the Real Number

  • The supply. The number you divide is the per-phase capacity your electrician states for charging, after the building’s other loads — a load calculation, which our guide to load calculation basics for adding EV chargers walks through. If it says the spare capacity is 70 A per phase, the honest count at full rate is two units, with little margin — not three and a hope.
  • The sockets. Each unit needs its own 32 A five-pin CEE socket on the board, fitted by an electrician, so the physical count can cap the plan before the supply does. Counting sockets is not a shortcut around the supply: ten sockets on a 64 A spare capacity still feed two units at full rate.
  • The need. Units that never run at the same time never draw together. Staggered windows — one shift’s vehicles in the evening, another’s after midnight — are the usage route when the supply cannot carry the peak. Portables add a lever fixed wallboxes lack: a unit can move to a different board or building as the pattern changes.

What This Model Will Not Do for the Plan

Automatic load sharing — chargers dividing a capped supply between themselves and rebalancing as vehicles finish — is a real technique, explained in our guide to dynamic load balancing. But this model’s listing does not state such a function, and it states no reduced-current setting to fall back on either. So the plan is capacity, staggering, or moving units — and if automatic sharing matters to your site, it is a written confirmation to obtain from EVDANCE before the board is designed around it.

The EV-ACS3205PE in a Multi-Unit Plan

The EV-ACS3205PE is a 22 kW three-phase portable charger: 32 A at 380–400 V, Type 2 connector, CEE five-pin plug, a 1.77-inch display, IP66 housing. In a load plan it behaves as a movable 32 A block: the same unit can serve a workshop board this month and a depot board next, and the plan changes by unplugging, not rewiring. Our CEE plugs explainer covers the socket side.

EVDANCE charging station equipment
A board can host several sockets — the supply behind it decides how many run at once.

EVDANCE is a Shenzhen manufacturer founded in 2011, exporting to more than 30 countries, and the unit carries its 3-year standard warranty.

Frequently Asked Questions

Can I run two units from a supply with 63 A per phase spare?

Not both at full rate. Two units ask for 64 A per phase before any other load, so the arithmetic leaves no headroom at all. The real answers are one unit at full rate, staggered use of the two, or a supply upgrade — and your electrician’s load calculation confirms which applies.

Does each unit need its own socket and circuit?

Plan on it. Each unit is a 32 A continuous load, and each plugs into its own five-pin CEE socket; how the board’s circuits are arranged and protected is the electrician’s design, made for the combined figure.

Can these units share a capped supply automatically?

No. No sharing or balancing function is published for this model, so treat it as a written-confirmation item. Until it is confirmed, plan on capacity or usage — the two routes above.

Related Reading

Sources & Standards

EVDANCE · EV Charger Manufacturer

Looking for a reliable EV charger supplier?

Portable EV chargers and wallbox home chargers for distributors, installers and brands. Tell us your market and we will reply with a quote.

  • OEM / ODM from 50 units
  • 3-year standard warranty
  • FOB / DDP shipping worldwide
Share the Post:

Related Posts

0