What Is the Best EV Charging Setup for a 20-Unit Apartment Building?

For 20 units there is no universal best setup — there is a sequence: count today's EV households, check the supply, start with a small shared pool, and wire for the expansion.

EVDANCE Insights · EV Charging Guides

There is no universal best setup for a 20-unit building — there is a sequence that finds yours. Count the households that actually drive EVs, have the building’s spare capacity confirmed by a licensed electrician, start with a small shared pool of Level 2 chargers under access control, and run the cable routes and capacity for the expansion at the same time. The worked example below shows the sequence end to end.

Key Takeaways

  • Sequence first: survey the EV households, confirm capacity in writing, then choose the layout.
  • Overnight dwell makes Level 2 pace ample; the binding constraint is cars charging at once, not speed.
  • A shared pool under access control is usually the right stage one at 20 units; prepare conduit and capacity for more.
  • Every example number here is invented — your survey count is the only figure that should size the install.
EV charging bays in a residential parking garage
Twenty units is small enough to survey by name, too small for borrowed ratios.

Step 1 and 2: Count Drivers, Then Capacity

  • Survey the building, not the market. List the households with an EV today and those who say they will buy one within the lease or ownership horizon. In a 20-unit building that list is short enough to be exact — it, not a national adoption figure, sets the first charger count.
  • Confirm capacity in writing. A licensed electrician checks the service and panel for spare capacity. Charging is a continuous load under the NEC, so each circuit is sized at 125% of the charger’s current: a 32 A charger sits on a 40 A circuit, a 48 A charger on a 60 A circuit.
  • Match power to the dwell. Residents park overnight, and Level 2 at 7–19 kW (U.S. DOT) adds roughly 10–20 miles of range per hour — overnight refills a daily commute many times over. Speed is not the constraint in a residential garage; simultaneous cars are.

Our guide to load calculation basics for buildings walks through how the capacity check is done.

Step 3: Choose the Layout

LayoutHow it worksFit at 20 units
Shared poolA few chargers in common bays; any resident with access can use them, sessions recorded per userUsually the right start — the chargers work every night instead of sitting at one household’s space
Assigned per householdA charger at each EV household’s own spaceClean cost attribution, but chargers idle when that household travels, and every new EV means a new install
HybridA shared pool now, with capacity and conduit prepared so assigned units can be addedThe phased answer — pool first, assignment later where demand proves permanent

Worked example — all figures invented for illustration. Say the survey finds 5 EV households today and 3 more likely within two years, in a building with 20 spaces. A defensible stage one: two dual-connector stations giving 4 shared bays, RFID access so each session is recorded to a household, and conduit plus panel capacity prepared for 4 more bays. If the survey had found 12 EV households instead, the same sequence argues for fitting more bays at once — the method is the content, not the numbers.

EVDANCE EV-ACT3204E 22 kW three-phase wallbox
One wallbox per bay, RFID deciding who may charge.

Hardware for the 20-Unit Scale

For shared bays, the EV-AC03201T dual-connector AC station puts two Type 2 connectors on one wallbox per bay, the EV-ACT3204PE is a 22 kW three-phase Type 2 wallbox with RFID and app control, IP66, CE. EVDANCE is a Shenzhen manufacturer founded in 2011, exports to 30+ countries, and carries a 3-year standard warranty. Building teams can start from the residential charging page.

Frequently Asked Questions

How many chargers should a 20-unit building start with?

As many as the survey of actual EV households supports as a shared pool — the worked example above starts with 4 bays for 5 EV households, but those figures are invented to show the method. Count your own drivers first; a ratio copied from another building sizes the wrong thing.

What if the panel cannot feed every charger at full power?

That is a design question for the project’s licensed electrician: circuits can be planned so the installed chargers run within the confirmed capacity — through charger ratings chosen for the supply, and staged fitting as capacity allows. Never solve it by oversizing breakers; the 125% continuous-load rule is not negotiable.

How do residents pay in a shared pool?

Sessions are recorded per user through RFID or the app, and the building settles them under its own written rule — per kWh where local rules allow, or as a periodic fee. Our guide to charging in shared apartment and condo parking covers the arrangements.

Related Reading

Sources & Standards

EVDANCE · EV Charger Manufacturer

Looking for a reliable EV charger supplier?

Portable EV chargers and wallbox home chargers for distributors, installers and brands. Tell us your market and we will reply with a quote.

  • OEM / ODM from 50 units
  • 3-year standard warranty
  • FOB / DDP shipping worldwide
Share the Post:

Related Posts

0